The brick cleaners came on Monday. They cleaned the bricks but in doing so, managed to soak the cornices which were stupidly stored in the garage (no garage door). Then it rained Monday, then Tuesday. I alerted the No-Name Building company of this issue first thing on Monday. No return calls.....Email sent in the afternoon.....No return calls or email. I have noticed that the construction people don't put anything in writing! Each time we have met, called etc, I have been making a point of summarising our conversations via email.....Anyway, my immediate concern was that the cornices would become so wet that they were unusable. A call to the Consrtuction Manager who assured us that the SS (did I tell you we have a new one?) would inspect it prior to installation to ensure it was ok to use. We are still waiting to hear the outcome, but are assuming everything was AOK as the gyprockers were up there yesterday cutting it to size, then installing it upstairs today
The electricians look as if they have paid a visit. Most of the electricals have now been pulled through the gyprock downstairs.
All I want is the stairs to be installed so I can take a good look around upstairs. I can only imagine what issues I will find there!
What else mmm....
The No-Name Building company recommended we put a header at the entry point to the study in case we wanted to closed it off in the future. I reluctantly agreed. At the time I thought it was suspicious being asked if we wanted something for free! I noticed yesterday that the header is a different size (height) to the other rooms with doors. A smaller door on that room will look quite odd when compared to the other upgraded doors downstairs. I have asked them to change this but are still waiting..........waiting....waiting........pass the popcorn......
Let me see if I have any photos to share........Oh, the other big news is that there are noticeable irregularities to approximately 15 bricks on the left hand side of the facade, Again, we have alerted the No-Name Building Company and are waiting for their response. Tomorrow I am going to send them a comprehensive email detailing everything that has not been addressed to date. In addition, I will create a post detailing the issues we have experienced to date with the No Name Building Company. Photos of the facade is below......
Search This Blog
Showing posts with label Gyprock. Show all posts
Showing posts with label Gyprock. Show all posts
Wednesday, December 7, 2011
Sunday, December 4, 2011
In the woods....with gyprocking
The internal gyprocking commenced on Friday and it appears to have been completed yesterday. (See photos below.
We sent an email last week to a senior executive detailing our concerns with the length of time it is taking to get the build done. Some weeks have gone by and only one small change has been done to the house. One other concern is the attitude we saw during the course of last week. The No-name Building company tried to use the quality inspection process as a means to hold us responsible for the build progressing. Despite providing a summary of issues noted by our building consultant on Monday , we were told the official report is required before gyprocking could commence (it was company policy!) . The official report was available later that day in any case. Again on Thursday, we were asked if it is ok to proceed to "gyprocking" and if it was, please send an email. As novices we are not aware if it is ok to proceed to gyprocking. As experts, the No Name Building Company is best to answer this. We do not know if the issues identified in the report have been fixed and have asked No Name Building Company to confirm. We do not know if there were issues with the PCA inspection nor do we know if it took place. We expect that No Name Building Company have its own only quality control processes in place and that reliance should not be placed on our building consultants report for this. Anyway, our concerns were voiced in email and on the phone. The assured us this was not the case.
We have also asked for a list of activities which are scheduled between now and Christmas. They have agreed to do this for us.
Let's wait and see.......
Hopefully the cornices and stairs will go in this week and I will be able to take a peak upstairs
We sent an email last week to a senior executive detailing our concerns with the length of time it is taking to get the build done. Some weeks have gone by and only one small change has been done to the house. One other concern is the attitude we saw during the course of last week. The No-name Building company tried to use the quality inspection process as a means to hold us responsible for the build progressing. Despite providing a summary of issues noted by our building consultant on Monday , we were told the official report is required before gyprocking could commence (it was company policy!) . The official report was available later that day in any case. Again on Thursday, we were asked if it is ok to proceed to "gyprocking" and if it was, please send an email. As novices we are not aware if it is ok to proceed to gyprocking. As experts, the No Name Building Company is best to answer this. We do not know if the issues identified in the report have been fixed and have asked No Name Building Company to confirm. We do not know if there were issues with the PCA inspection nor do we know if it took place. We expect that No Name Building Company have its own only quality control processes in place and that reliance should not be placed on our building consultants report for this. Anyway, our concerns were voiced in email and on the phone. The assured us this was not the case.
We have also asked for a list of activities which are scheduled between now and Christmas. They have agreed to do this for us.
Let's wait and see.......
Hopefully the cornices and stairs will go in this week and I will be able to take a peak upstairs
| Kitchen, dining, rumpus and lounge |
| Looking back from Rumpus room |
| My quiet "white room" |
| Front entry, stairs to go on left side |
| Downstairs powder room |
| Looking at front door |
| Laundry |
| Kitchen with Butlers Pantry (far right door), large left hand cavity is for the fridge, and the smaller cavity is for draws and overhead cupboards. Window spashback to the right where oven will sit |
| Downstairs linen cupboard |
| Garage - taken before the gyprocking was completed |
| Media Room |
Friday, November 4, 2011
In the woods...with an update
Well, well, well..the brickies finally finished today. Amazing..... that seemed to drag on forever....... On Monday the bricks should be cleaned, so I will reserve my judgement until then.
I got the brickies a case of beer as a thank you. Hopefully the news spreads and the other tradies will carry out their work with diligence and effeciency so we can get into the house! Somehow, I don't think a case of beer will cut it.
So, what is planned for the next week or so?
- Roof tiles to be replaced (supposed to be yesterday and today, but I am not sure what has happened)
- Monday is brick cleaning
- Tuesday eaves gyprocking and painting
I have some pics to share with you now, but will take some after the bricks have been cleaned.
What else can I tell you? Our lovely neighbours behind are doing a KDR with the same building company as us. They are at DA stage, cant wait to see their house go up.We were lucky to receive a $500 referral cheque from the no-name Building company which we are going to split with them.
The other big news is that no. 19 (the white house in some of my pics) next to us has sold and they have just submitted a DA to council on behalf of the new owners who live next door! (the house doesn't settle until December, so I guess they are doing the new owners a favour by submitting it). My beautiful neighbours on the other side moved out today. They were such nice gentlemen.
So lots happening around us .
I got the brickies a case of beer as a thank you. Hopefully the news spreads and the other tradies will carry out their work with diligence and effeciency so we can get into the house! Somehow, I don't think a case of beer will cut it.
So, what is planned for the next week or so?
- Roof tiles to be replaced (supposed to be yesterday and today, but I am not sure what has happened)
- Monday is brick cleaning
- Tuesday eaves gyprocking and painting
I have some pics to share with you now, but will take some after the bricks have been cleaned.
What else can I tell you? Our lovely neighbours behind are doing a KDR with the same building company as us. They are at DA stage, cant wait to see their house go up.We were lucky to receive a $500 referral cheque from the no-name Building company which we are going to split with them.
The other big news is that no. 19 (the white house in some of my pics) next to us has sold and they have just submitted a DA to council on behalf of the new owners who live next door! (the house doesn't settle until December, so I guess they are doing the new owners a favour by submitting it). My beautiful neighbours on the other side moved out today. They were such nice gentlemen.
So lots happening around us .
| Front Entry |
| My "quiet" front room, where I will sit and watch the passing parade free of kids |
| Powder room downstairs |
| Butlers Pantry (2nd kitchen to be fitted out when we move in) |
| Laundry |
| Kitchen with glass window splashback |
| Lounge/ Dining |
| Rumpus looking back into lounge/ dining/kitchen |
| Rumpus looking over to Alfresco |
| Alfresco area (roof still to be laid) |
| Looking from Kitchen to backyard |
| Double garage |
| Media or spare room? Still undecided |