The kitchen and bathroom vanities were delivered today ready for installation tomorrow. The white poly kitchen, powder room, and main bathroom all look great. I am really happy we upgraded. The en-suite double vanity was unfortunately in white poly too and not nocturne oak. You know what that means! Delays.
What else....mmmm....I just received an alternate solution to the stair problem.....Just considering it now.
Tiling has slowed to a halt. Yesterday there were 4 tilers, 3 this morning and 1 when I visited this afternoon. Problem? They had run out of tiles. Of course I called the SS and told him about the tile and vanity situation.....I am so glad we live one block away and can monitor what is happening at the house several times per day!
I also received a quote today for fitting out the Butlers Pantry. A relative recommended and used this company recently for a poly/ ceasarstone kitchen. Timpelle Kitchen wanted $4800 for a 3 metre line laminate under bench cabinetry. I am getting 3 metres of white poly, sharknose under bench and above bench cabinetry! This is with a gloss laminate top. If I want to upgrade to Ceasarstone it is an additional $1500. My husband thinks we should get the ceasarstone so it matches the main kitchen 100%.....it may be overkill though for a second kitchen? Bye
Search This Blog
Showing posts with label Timpelle Kitchens. Show all posts
Showing posts with label Timpelle Kitchens. Show all posts
Tuesday, January 17, 2012
Friday, December 16, 2011
In the woods.....with a pre-Xmas Update
Did the drive by about an hour ago and noticed the garage door had been installed. Its Dune in colour but sometimes looks, grey sometimes white, and sometimes cream depending on the light. Our bricks have the same illusion, sometimes black black, sometimes brown.......
Spoke to my SS who said the plan was to:
- Install stairs will happen next Monday
- The carpenters will return next Wednesday and work through the Xmas break
- Timpelle Kitchens booked tentatively for 17 January
- The Admin people at the No-Name Building company cant find my paperwork for Di-Lorenzo so this cant be booked in for January yet. Fingers crossed they find it today.
No Name Building company and our SS officially close for Xmas next Friday and re-open on the 9th January. We are so pleased that they have organised tradespeople to work through.
Spoke to my SS who said the plan was to:
- Install stairs will happen next Monday
- The carpenters will return next Wednesday and work through the Xmas break
- Timpelle Kitchens booked tentatively for 17 January
- The Admin people at the No-Name Building company cant find my paperwork for Di-Lorenzo so this cant be booked in for January yet. Fingers crossed they find it today.
No Name Building company and our SS officially close for Xmas next Friday and re-open on the 9th January. We are so pleased that they have organised tradespeople to work through.
Thursday, October 13, 2011
In the woods....With the latest
Bricking News
Bricklayers returned yesterday. They will be laying bricks for another week or so. Had a chat to the brickie who asked if I was happy with their work? Hello, are you stupid, why on earth would I complain if I was happy? I shouldn't be so mean........
Kitchen News
Yesterday I received a call from Timpelle Kitchens advising they would need to reduce the draws and kitchen bench by 10cm because of the increased size of the fridge cavity. The issue lies with the No-Name Building company not taking the wall back under the stairs. Instead, they pulled the fridge cavity wall forward taking up valuable kitchen space! Timpelle picked this up when the went to the house to do a final measure. Spoke to Shane our SS about it yesterday. He is checking it out today.
Plumbing News
In addition to this, our SS also mentioned Timpelle Kitchens sent him an email saying the kitchen plumbing is in the incorrect place and needs to be moved! WTF??? How did that happen???? Again, our SS will check this out today. I wonder how they move it? I think they will need to dig up the slab.?
Fingers crossed I will get some answers to the Roof tiles, kitchen plumbing and Fridge cavity today.
All I can say is thank goodness Timpelle is on the ball
Bricklayers returned yesterday. They will be laying bricks for another week or so. Had a chat to the brickie who asked if I was happy with their work? Hello, are you stupid, why on earth would I complain if I was happy? I shouldn't be so mean........
Kitchen News
Yesterday I received a call from Timpelle Kitchens advising they would need to reduce the draws and kitchen bench by 10cm because of the increased size of the fridge cavity. The issue lies with the No-Name Building company not taking the wall back under the stairs. Instead, they pulled the fridge cavity wall forward taking up valuable kitchen space! Timpelle picked this up when the went to the house to do a final measure. Spoke to Shane our SS about it yesterday. He is checking it out today.
Plumbing News
In addition to this, our SS also mentioned Timpelle Kitchens sent him an email saying the kitchen plumbing is in the incorrect place and needs to be moved! WTF??? How did that happen???? Again, our SS will check this out today. I wonder how they move it? I think they will need to dig up the slab.?
Fingers crossed I will get some answers to the Roof tiles, kitchen plumbing and Fridge cavity today.
All I can say is thank goodness Timpelle is on the ball